Re: [ADMIN] Schedule Update

Edward Burns
 

On Fri, 21 Jul 2017 15:21:38 -0700, Edward Burns <@edburns> said:
EB> Due to one final TCK change and a small spec wording change we had to
EB> delay handing the FAB to JCP by one week. The revised schedule is:

EB> 2017-07-25 Hand FAB materials to JCP

EB> 2017-08-01 14 Day FAB Start

EB> 2017-08-16 14 Day FAB End

EB> I'm going on vacation next week, but Shing-wai will be working to answer
EB> any questions you may have.

We are currently in FAB!

Ed

--